European Programs / Improvement of the production capacity and increase of the exports of “Vrangovi” Ltd.
Improvement of the production capacity and increase of the exports of “Vrangovi” Ltd.
BG16FOP002-2.001-0203-C01
Program Overview
PROJECT: “Improvement of the production capacity and increase of the exports of Vrangovi Ltd.”
CONTRACT: BG16FOP002-2.001-0203-C01
The implementation of Grant Agreement No. BG16FOP002-2.001-0203-C01 was completed on 10.02.2017. In connection with the completion of the activities, the final report under the contract was submitted on 02.03.2017. In March, an on-site inspection was also carried out by the Managing Authority. All machines included in the project have been delivered and put into operation. Starting from 2018, the indicators set out in the project and in the grant agreement began to be implemented.
The results achieved and expected to be achieved within 3 years after the implementation of the project are:
CNC hydraulic press brake
Band saw machine
MIG/MAG welding machine
MIG/MAG welding machine
CNC hydraulic guillotine shear
Plasma cutting equipment
Single-girder overhead crane with lifting capacity Q = 5 t and span Lk = 10.50 m
Documents for the selection of suppliers
In connection with the implementation of Grant Agreement No. BG16RFOP002-2.001-0203-C01 and the conduct of contractor selection procedures, we publish the tender documentation for the selection of contractors:
Delivery and installation of a single-girder overhead crane with lifting capacity Q = 5 t and span Lk = 10.50 m.
Delivery and installation of machines in separate lots.